Action Date | Action Description |
---|---|
Jul 03, 2019 | Assent Application Received |
Jul 03, 2019 | Administrative Review for Completeness |
Jul 16, 2019 | Team Review for Completeness |
Jul 16, 2019 | Deficient Application - Owner Notification Sent |
Sep 26, 2019 | Meeting Held |
Jan 07, 2020 | Note to File |
Jan 04, 2021 | Additional Information Received |
Nov 12, 2021 | Deficiency Response Received |
Nov 17, 2021 | Bio Team Review for Completeness |
Nov 17, 2021 | Application Accepted |
Nov 17, 2021 | Project Manager |
Nov 23, 2021 | HPHC Historical Preservation No Effect |
Nov 23, 2021 | HPHC Review Pending |
Feb 10, 2022 | Biologist Report |
Feb 16, 2022 | Permit Approved |
Feb 16, 2022 | Typist for Processing |
Feb 16, 2022 | Executive Sign Off |
Feb 16, 2022 | Sent to Photo Copy |
Feb 18, 2022 | Permit Mailed |
Feb 28, 2022 | Land Evidence Date |
Nov 15, 2022 | Commencement of Work Notice received |