Action Date | Action Description |
---|---|
Aug 14, 2019 | Assent Application Received |
Aug 14, 2019 | Administrative Review for Completeness |
Aug 23, 2019 | Team Review for Completeness |
Aug 23, 2019 | Application Accepted |
Oct 16, 2019 | HPHC Review Pending |
Oct 16, 2019 | HPHC Historical Preservation No Effect |
Apr 16, 2020 | Additional Information Received |
Jul 24, 2020 | Additional Information Received |
Aug 21, 2020 | Plans Received |
Aug 21, 2020 | Additional Information Received |
Sep 21, 2020 | Biologist Report |
Sep 22, 2020 | Typist for Processing |
Sep 22, 2020 | Executive Sign Off |
Sep 22, 2020 | Sent to Photo Copy |
Sep 22, 2020 | Permit Approved |
Sep 29, 2020 | Land Evidence Date |
Oct 06, 2022 | Assent Requirement |