Action Date | Action Description |
---|---|
Sep 06, 2019 | Assent Application Received |
Sep 09, 2019 | Administrative Review for Completeness |
Sep 09, 2019 | Team Review for Completeness |
Sep 16, 2019 | Application Accepted |
Oct 16, 2019 | HPHC Review Pending |
Oct 16, 2019 | HPHC Historical Preservation No Effect |
Oct 17, 2019 | Plans Received |
Oct 17, 2019 | Additional Information Received |
Nov 14, 2019 | Biologist Report |
Nov 15, 2019 | Typist for Processing |
Nov 15, 2019 | Executive Sign Off |
Nov 15, 2019 | Sent to Photo Copy |
Nov 15, 2019 | Permit Approved |
Nov 26, 2019 | Land Evidence Date |