Action Date | Action Description |
---|---|
Conservation Easement Recording received | |
Oct 16, 2019 | Assent Application Received |
Oct 17, 2019 | Administrative Review for Completeness |
Oct 28, 2019 | Bio Team Review for Completeness |
Oct 28, 2019 | Eng Team Review for Completeness |
Oct 28, 2019 | Application Accepted |
Nov 07, 2019 | HPHC Review Pending |
Nov 07, 2019 | HPHC Historical Preservation No Effect |
Dec 24, 2019 | Additional Information Received |
Jan 10, 2020 | 15 day Public Notice Issued |
Jan 25, 2020 | Public Notice End Date |
Feb 14, 2020 | Plans Received |
Feb 19, 2020 | Biologist Report |
Feb 24, 2020 | Engineering Report |
Feb 24, 2020 | Plans Received |
Feb 25, 2020 | Typist for Processing |
Feb 25, 2020 | Executive Sign Off |
Feb 25, 2020 | Sent to Photo Copy |
Feb 25, 2020 | Permit Approved |
Mar 13, 2020 | Assent Correction Mailed |
Mar 13, 2020 | Phone Call |
Apr 06, 2020 | Land Evidence Date |
Apr 17, 2020 | Conservation Easement Mailed. |