Action Date | Action Description |
---|---|
Dec 06, 2019 | Bio Team Review for Completeness |
Feb 05, 2020 | Assent Application Received |
Feb 05, 2020 | Administrative Review for Completeness |
Feb 14, 2020 | Eng Team Review for Completeness |
Feb 14, 2020 | Application Accepted |
Feb 14, 2020 | Category B assigned |
Feb 25, 2020 | HPHC Historical Preservation No Effect |
Feb 25, 2020 | HPHC Review Pending |
Mar 20, 2020 | 30 day Public Notice Issued |
Apr 20, 2020 | Public Notice End Date |
Jun 22, 2020 | Typist for Processing |
Jun 22, 2020 | Executive Sign Off |
Jun 22, 2020 | Sent to Photo Copy |
Jun 22, 2020 | Permit Approved |
Jun 22, 2020 | Engineering Report |
Jun 22, 2020 | Biologist Report |
Jun 29, 2020 | Land Evidence Date |