Action Date | Action Description |
---|---|
Feb 18, 2020 | Maintenance Certification Request |
Feb 18, 2020 | Administrative Review for Completeness |
Feb 20, 2020 | Bio Team Review for Completeness |
Feb 20, 2020 | Deficient Application - Owner Notification Sent |
May 18, 2020 | Deficiency Response Received |
May 19, 2020 | Bio Team Review for Completeness |
May 19, 2020 | Application Accepted |
May 19, 2020 | Project Manager |
May 19, 2020 | Biologist Report |
May 19, 2020 | Typist for Processing |
May 19, 2020 | Executive Sign Off |
May 19, 2020 | Sent to Photo Copy |
May 19, 2020 | Permit Approved |