Action Date | Action Description |
---|---|
Feb 19, 2020 | Assent Application Received |
Feb 19, 2020 | Administrative Review for Completeness |
Feb 24, 2020 | Bio Team Review for Completeness |
Feb 24, 2020 | Application Accepted |
Feb 26, 2020 | Plans Received |
Mar 06, 2020 | Project Manager |
Mar 09, 2020 | HPHC Historical Preservation No Effect |
Mar 09, 2020 | HPHC Review Pending |
Mar 11, 2020 | Biologist Report |
Mar 13, 2020 | Typist for Processing |
Mar 13, 2020 | Executive Sign Off |
Mar 13, 2020 | Sent to Photo Copy |
Mar 13, 2020 | Permit Approved |
Mar 30, 2020 | Land Evidence Date |
Jan 13, 2023 | Extension of Permit Request |
Jan 26, 2023 | Modification Request |
Jan 30, 2023 | Administrative Review for Completeness |
Feb 06, 2023 | Bio Team Review for Completeness |
Feb 06, 2023 | Project Manager |
Mar 10, 2023 | HPHC Historical Preservation No Effect |
Mar 27, 2023 | Biologist Report |
Mar 29, 2023 | Extension Approved |
Mar 29, 2023 | Typist for Processing |
Mar 29, 2023 | Executive Sign Off |
Mar 29, 2023 | Sent to Photo Copy |
Mar 29, 2023 | Modification Approved |