Action Date | Action Description |
---|---|
Feb 27, 2020 | Freshwater Wetland - Preliminary Determination |
Feb 27, 2020 | Administrative Review for Completeness |
Mar 12, 2020 | Bio Team Review for Completeness |
Mar 12, 2020 | Deficient Application - Owner Notification Sent |
Jun 10, 2020 | Deficiency Response Received |
Jun 10, 2020 | Administrative Review for Completeness |
Jun 25, 2020 | Bio Team Review for Completeness |
Sep 02, 2020 | Deficiency Response Received |
Sep 14, 2020 | Administrative Review for Completeness |
Sep 16, 2020 | Application Accepted |
Sep 16, 2020 | Project Manager |
Sep 16, 2020 | Bio Team Review for Completeness |
Sep 16, 2020 | Eng Team Review for Completeness |
Sep 22, 2020 | HPHC Review Pending |
Sep 22, 2020 | Engineering Report |
Sep 22, 2020 | Biologist Report |
Sep 22, 2020 | Typist for Processing |
Sep 22, 2020 | Executive Sign Off |
Sep 22, 2020 | Sent to Photo Copy |
Sep 22, 2020 | Permit Approved |
Sep 22, 2020 | HPHC Historical Preservation Comments/Concerns |
Jan 14, 2021 | Land Evidence Date |
Jan 14, 2021 | HPHC Historical Preservation No Effect |