Action Date | Action Description |
---|---|
Aug 07, 2020 | Assent Application Received |
Sep 02, 2020 | Administrative Review for Completeness |
Sep 02, 2020 | Bio Team Review for Completeness |
Sep 02, 2020 | Deficient Application - Owner Notification Sent |
Sep 14, 2020 | Deficient Application Picked Up |
Feb 02, 2021 | Deficiency Response Received |
Feb 08, 2021 | Bio Team Review for Completeness |
Feb 08, 2021 | Application Accepted |
Feb 09, 2021 | Project Manager |
Feb 17, 2021 | HPHC Review Pending |
Feb 17, 2021 | HPHC Historical Preservation No Effect |
Mar 29, 2021 | Plans Received |
Mar 30, 2021 | Additional Information Received |
Apr 05, 2021 | Additional Information Received |
Apr 05, 2021 | Stipulation Package from Biologist |
Apr 05, 2021 | Biologist Report |
Apr 06, 2021 | Typist for Processing |
Apr 06, 2021 | Executive Sign Off |
Apr 06, 2021 | Sent to Photo Copy |
Apr 06, 2021 | Permit Approved |
Jun 21, 2021 | Land Evidence Date |