Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Sep 10, 2020 | Assent Application Received |
Sep 18, 2020 | Administrative Review for Completeness |
Oct 13, 2020 | Category A* (Docks) |
Oct 16, 2020 | Bio Team Review for Completeness |
Dec 09, 2020 | Deficient Application Picked Up |
Dec 31, 2020 | Deficiency Response Received |
Jan 05, 2021 | Bio Team Review for Completeness |
Jan 05, 2021 | Application Accepted |
Jan 06, 2021 | Project Manager |
Jan 15, 2021 | Plans Received |
Jan 21, 2021 | HPHC Historical Preservation No Effect |
Jan 21, 2021 | HPHC Review Pending |
Mar 01, 2021 | 30 day Public Notice Issued |
Mar 29, 2021 | Objections/Comments Received |
Mar 29, 2021 | Objections/Comments Received |
Apr 01, 2021 | Comments Received |
Apr 01, 2021 | Public Notice End Date |
Oct 05, 2021 | Additional Information Received |
Nov 01, 2021 | 30 day Public Notice Issued |
Nov 02, 2021 | Comments Received |
Dec 01, 2021 | Public Notice End Date |
Mar 10, 2022 | Biologist Report |
Mar 10, 2022 | Engineering Report |
Mar 14, 2022 | Mail Agenda Notice |
Mar 22, 2022 | Council Approval Granted |
Mar 22, 2022 | Semi-Monthly Meeting Date Scheduled |
Aug 24, 2022 | Legal Response/Decision |
Aug 24, 2022 | 30 Day Appeal Notification to Owner |
Sep 29, 2022 | Stipulation Package from Biologist |
Oct 03, 2022 | Typist for Processing |
Oct 03, 2022 | Executive Sign Off |
Oct 03, 2022 | Sent to Photo Copy |
Oct 03, 2022 | Permit Approved |
Oct 11, 2022 | Permit Mailed |
Oct 21, 2022 | Land Evidence Date |