Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Sep 30, 2020 | Assent Application Received |
Oct 01, 2020 | Administrative Review for Completeness |
Oct 08, 2020 | Bio Team Review for Completeness |
Oct 09, 2020 | Category A* (Docks) |
Oct 09, 2020 | Application Accepted |
Oct 09, 2020 | Project Manager |
Oct 27, 2020 | HPHC Review Pending |
Oct 27, 2020 | HPHC Historical Preservation No Effect |
Nov 06, 2020 | 30 day Public Notice Issued |
Nov 24, 2020 | Correspondence Received |
Dec 06, 2020 | Public Notice End Date |
Jan 08, 2021 | Dock Meeting -- Approval |
Jan 20, 2021 | Stipulation Package from Biologist |
Jan 20, 2021 | Typist for Processing |
Jan 20, 2021 | Executive Sign Off |
Jan 20, 2021 | Sent to Photo Copy |
Jan 20, 2021 | Permit Approved |
Jan 20, 2021 | Biologist Report |
Feb 16, 2021 | Land Evidence Date |