Action Date | Action Description |
---|---|
Oct 08, 2020 | Bio Team Review for Completeness |
Oct 08, 2020 | Application Accepted |
Oct 08, 2020 | Assent Application Received |
Oct 08, 2020 | Administrative Review for Completeness |
Oct 09, 2020 | Project Manager |
Oct 16, 2020 | Plans Received |
Oct 26, 2020 | HPHC Historical Preservation No Effect |
Oct 26, 2020 | HPHC Review Pending |
Nov 30, 2020 | Plans Received |
Dec 08, 2020 | Stipulation Package from Biologist |
Dec 08, 2020 | Typist for Processing |
Dec 08, 2020 | Executive Sign Off |
Dec 08, 2020 | Sent to Photo Copy |
Dec 08, 2020 | Permit Approved |
Dec 08, 2020 | Biologist Report |
Jun 15, 2021 | Duplicate Original Assent requested/mailed |
Jun 18, 2021 | Land Evidence Date |