Action Date | Action Description |
---|---|
Oct 16, 2020 | Assent Application Received |
Oct 19, 2020 | Administrative Review for Completeness |
Oct 23, 2020 | Bio Team Review for Completeness |
Oct 23, 2020 | Application Accepted |
Oct 26, 2020 | Project Manager |
Nov 25, 2020 | HPHC Review Pending |
Nov 25, 2020 | HPHC Historical Preservation No Effect |
Nov 30, 2020 | Additional Information Received |
Nov 30, 2020 | CHA Worksheet received |
Dec 07, 2020 | Additional Information Received |
Dec 22, 2020 | Biologist Report |
Dec 22, 2020 | Typist for Processing |
Dec 22, 2020 | Executive Sign Off |
Dec 22, 2020 | Sent to Photo Copy |
Dec 22, 2020 | Permit Approved |
Jan 06, 2021 | Land Evidence Date |
Aug 04, 2021 | Modification Request |
Aug 10, 2021 | Administrative Review for Completeness |
Aug 18, 2021 | Bio Team Review for Completeness |
Aug 19, 2021 | Project Manager |
Sep 03, 2021 | HPHC Historical Preservation No Effect |
Sep 03, 2021 | HPHC Review Pending |
Aug 22, 2022 | 30-Day Notification of Cancellation letter |
Sep 29, 2022 | Application Cancelled |
Sep 29, 2022 | Biologist Report |