Application 2020-11-083 Details

Back to List


Actions:

Action Date Action Description
Dock Post-Construction Certification by Engineer received.
Nov 18, 2020 Assent Application Received
Nov 20, 2020 Administrative Review for Completeness
Nov 25, 2020 Category A* (Docks)
Dec 01, 2020 Bio Team Review for Completeness
Dec 02, 2020 Application Accepted
Dec 02, 2020 Project Manager
Dec 02, 2020 Category A* (Docks)
Dec 02, 2020 30 day Public Notice Issued
Dec 23, 2020 HPHC Review Pending
Dec 23, 2020 HPHC Historical Preservation No Effect
Jan 02, 2021 Public Notice End Date
Jan 21, 2021 Plans Received
Jan 29, 2021 Biologist Report
Feb 01, 2021 Mail Agenda Notice
Feb 04, 2021 Supervisor Biologist SignOff
Feb 04, 2021 Supervisor Engineer SignOff
Feb 04, 2021 Executive Signoff of Staff Reports
Feb 09, 2021 Semi-Monthly Meeting Date Scheduled
Feb 10, 2021 Typist for Processing
Feb 10, 2021 Executive Sign Off
Feb 10, 2021 Sent to Photo Copy
Feb 10, 2021 Permit Approved
Feb 19, 2021 Land Evidence Date

Details:

File No
2020-11-083
Town
Narragansett
First Name
Eric
Last Name
Hedison Revocable Living Trust
Street
Mollusk Drive
Location
15 Mollusk Drive
Plat/Map
R-2
Lot/Block
340
Decision Date
Feb 10, 2021
Dock Reg.No
2421
Project
c/m new residential boating facility
Description
Docks, Piers, Floats (Residential)
Water Area
Point Judith Pond (Great Island)
Easement
0
Acceptance Date
Dec 02, 2020