Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Nov 18, 2020 | Assent Application Received |
Nov 20, 2020 | Administrative Review for Completeness |
Nov 25, 2020 | Category A* (Docks) |
Dec 01, 2020 | Bio Team Review for Completeness |
Dec 02, 2020 | Application Accepted |
Dec 02, 2020 | Project Manager |
Dec 02, 2020 | Category A* (Docks) |
Dec 02, 2020 | 30 day Public Notice Issued |
Dec 23, 2020 | HPHC Review Pending |
Dec 23, 2020 | HPHC Historical Preservation No Effect |
Jan 02, 2021 | Public Notice End Date |
Jan 21, 2021 | Plans Received |
Jan 29, 2021 | Biologist Report |
Feb 01, 2021 | Mail Agenda Notice |
Feb 04, 2021 | Supervisor Biologist SignOff |
Feb 04, 2021 | Supervisor Engineer SignOff |
Feb 04, 2021 | Executive Signoff of Staff Reports |
Feb 09, 2021 | Semi-Monthly Meeting Date Scheduled |
Feb 10, 2021 | Typist for Processing |
Feb 10, 2021 | Executive Sign Off |
Feb 10, 2021 | Sent to Photo Copy |
Feb 10, 2021 | Permit Approved |
Feb 19, 2021 | Land Evidence Date |