Action Date | Action Description |
---|---|
HPHC Review Pending | |
CHA -- application modified due to CHA info | |
Jan 05, 2021 | Freshwater Wetland - Request to Alter |
Jan 05, 2021 | Administrative Review for Completeness |
Jan 06, 2021 | Application Accepted |
Jan 06, 2021 | Bio Team Review for Completeness |
Feb 02, 2021 | Engineering Report |
Feb 02, 2021 | Biologist Report |
Feb 02, 2021 | Stipulation Package by Engineer |
Feb 02, 2021 | Stipulation Package from Biologist |
Feb 02, 2021 | Typist for Processing |
Feb 02, 2021 | Executive Sign Off |
Feb 02, 2021 | Sent to Photo Copy |
Feb 02, 2021 | Permit Approved |
Jan 13, 2022 | Land Evidence Date |