Action Date | Action Description |
---|---|
Biologist Report | |
Project Manager | |
Jan 28, 2021 | Assent Application Received |
Feb 01, 2021 | Administrative Review for Completeness |
Feb 08, 2021 | Bio Team Review for Completeness |
Feb 08, 2021 | Project Manager |
Feb 08, 2021 | Application Accepted |
Feb 09, 2021 | Category A* (Docks) |
Feb 17, 2021 | HPHC Historical Preservation No Effect |
Feb 17, 2021 | HPHC Review Pending |
Mar 08, 2021 | Plans Received |
Mar 26, 2021 | 30 day Public Notice Issued |
Apr 26, 2021 | Public Notice End Date |
May 08, 2021 | Correspondence Received |
May 13, 2021 | Additional Information Received |
Jun 01, 2021 | Letter of Support for Project |
Jun 17, 2021 | Biologist Report |
Jun 17, 2021 | Dock Meeting -- Approval |
Jun 17, 2021 | Stipulation Package from Biologist |
Jun 21, 2021 | Typist for Processing |
Jun 21, 2021 | Permit Approved |
Jun 21, 2021 | Sent to Photo Copy |
Jun 21, 2021 | Executive Sign Off |
Jul 19, 2021 | Land Evidence Date |
Jul 19, 2021 | Dock Post-Construction Certification by Engineer received. |
Feb 14, 2024 | Modification Request |
Feb 19, 2024 | Administrative Review for Completeness |
Feb 22, 2024 | Bio Team Review for Completeness |
Feb 22, 2024 | Project Manager |
Feb 22, 2024 | Application Accepted |
Mar 08, 2024 | HPHC Historical Preservation No Effect |