Action Date | Action Description |
---|---|
Apr 08, 2021 | Violation Exists on this Site (NOV) |
Apr 08, 2021 | Maintenance Certification Request |
Apr 08, 2021 | Administrative Review for Completeness |
May 06, 2021 | Application Accepted |
May 06, 2021 | Bio Team Review for Completeness |
May 07, 2021 | Project Manager |
May 17, 2021 | HPHC Review Pending |
May 17, 2021 | HPHC Historical Preservation No Effect |
Jun 29, 2021 | Plans Received |
Jul 27, 2021 | Stipulation Package from Biologist |
Aug 05, 2021 | Stipulation Package from Biologist |
Aug 05, 2021 | Biologist Report |
Aug 11, 2021 | Permit Approved |
Aug 11, 2021 | Typist for Processing |
Aug 11, 2021 | Executive Sign Off |
Aug 11, 2021 | Sent to Photo Copy |
Aug 12, 2021 | Permit Mailed |
Oct 27, 2021 | Assent Requirement |
Jan 10, 2022 | Land Evidence Date |