Action Date | Action Description |
---|---|
Apr 27, 2021 | Assent Application Received |
May 03, 2021 | Administrative Review for Completeness |
May 06, 2021 | Additional Information Received |
May 06, 2021 | Bio Team Review for Completeness |
Jun 25, 2021 | Deficient Application - Owner Notification Sent |
Oct 28, 2021 | Deficiency Response Received |
Nov 02, 2021 | Bio Team Review for Completeness |
Nov 02, 2021 | Application Accepted |
Nov 02, 2021 | Project Manager |
Nov 09, 2021 | HPHC Review Pending |
Dec 14, 2021 | Plans Received |
Jan 13, 2022 | HPHC Historical Preservation No Effect |
Jan 13, 2022 | Biologist Report |
Jan 19, 2022 | Permit Approved |
Jan 19, 2022 | Typist for Processing |
Jan 19, 2022 | Executive Sign Off |
Jan 19, 2022 | Sent to Photo Copy |
Jan 20, 2022 | Permit Mailed |
Jan 17, 2023 | Land Evidence Date |
Aug 08, 2024 | Commencement of Work Notice received |