Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Enforcement Compliance Inspection Required | |
May 19, 2021 | Assent Application Received |
May 20, 2021 | Administrative Review for Completeness |
May 28, 2021 | Bio Team Review for Completeness |
May 28, 2021 | Application Accepted |
Jun 14, 2021 | Project Manager |
Jun 28, 2021 | HPHC Review Pending |
Jun 28, 2021 | HPHC Historical Preservation No Effect |
Jul 19, 2021 | 30 day Public Notice Issued |
Jul 21, 2021 | US Army Corps of Engineers Approval Received |
Aug 19, 2021 | Public Notice End Date |
Sep 01, 2021 | Biologist Report |
Sep 01, 2021 | Stipulation Package from Biologist |
Sep 01, 2021 | Typist for Processing |
Sep 01, 2021 | Category A* (Docks) |
Sep 01, 2021 | Executive Sign Off |
Sep 01, 2021 | Sent to Photo Copy |
Sep 01, 2021 | Permit Approved |
Sep 03, 2021 | Permit Mailed |
Sep 13, 2021 | Land Evidence Date |
Jul 22, 2024 | Extension of Permit Request |