Action Date | Action Description |
---|---|
Assent Requirement | |
Aug 11, 2021 | Assent Application Received |
Aug 25, 2021 | Administrative Review for Completeness |
Aug 31, 2021 | Additional Information Received |
Sep 01, 2021 | Additional Information Received |
Sep 01, 2021 | Application Accepted |
Sep 01, 2021 | Project Manager |
Sep 01, 2021 | Bio Team Review for Completeness |
Sep 15, 2021 | Plans Received |
Sep 17, 2021 | Stipulation Package from Biologist |
Sep 17, 2021 | Biologist Report |
Oct 05, 2021 | HPHC Review Pending |
Oct 05, 2021 | HPHC Historical Preservation No Effect |
Oct 07, 2021 | Typist for Processing |
Oct 07, 2021 | Executive Sign Off |
Oct 07, 2021 | Sent to Photo Copy |
Oct 07, 2021 | Permit Approved |
Oct 12, 2021 | Permit Mailed |
Nov 03, 2021 | Land Evidence Date |
Sep 04, 2024 | Extension of Permit Request |
Oct 01, 2024 | Enforcement Compliance Inspection Required |
Oct 09, 2024 | Process Extension |
Oct 09, 2024 | Extension Approved |