Aug 25, 2021 | Assent Application Received |
Aug 31, 2021 | Administrative Review for Completeness |
Sep 01, 2021 | Eng Team Review for Completeness |
Sep 01, 2021 | Bio Team Review for Completeness |
Sep 01, 2021 | Application Accepted |
Sep 01, 2021 | Project Manager |
Oct 01, 2021 | HPHC Review Pending |
Oct 01, 2021 | HPHC Historical Preservation No Effect |
Oct 21, 2021 | 30 day Public Notice Issued |
Nov 21, 2021 | Public Notice End Date |
Feb 18, 2022 | Public Hearing Notices Mailed |
Mar 01, 2022 | Biologist Report |
Mar 01, 2022 | Engineering Report |
Mar 01, 2022 | Additional Information Received |
Mar 22, 2022 | Council Approval Granted |
Mar 22, 2022 | Semi-Monthly Meeting Date Scheduled |
Mar 24, 2022 | Stipulation Package by Engineer |
Mar 29, 2022 | Permit Approved |
Mar 29, 2022 | Typist for Processing |
Mar 29, 2022 | Executive Sign Off |
Mar 29, 2022 | Sent to Photo Copy |
Mar 30, 2022 | Permit Mailed |
Apr 07, 2022 | Land Evidence Date |
Nov 17, 2023 | Modification Request |
Nov 21, 2023 | Administrative Review for Completeness |
Dec 14, 2023 | Bio Team Review for Completeness |
Dec 14, 2023 | Modification Approved |