Action Date | Action Description |
---|---|
Feb 22, 2022 | Assent Application Received |
Mar 02, 2022 | Administrative Review for Completeness |
Mar 02, 2022 | Bio Team Review for Completeness |
Mar 02, 2022 | Application Accepted |
Mar 07, 2022 | Project Manager |
Mar 07, 2022 | Bio Team Review for Completeness |
Mar 24, 2022 | HPHC Review Pending |
Mar 24, 2022 | HPHC Historical Preservation No Effect |
Apr 06, 2022 | Objections/Comments Received |
Apr 07, 2022 | Objections/Comments Received |
Apr 11, 2022 | Objections/Comments Received |
Apr 11, 2022 | Objections/Comments Received |
Apr 11, 2022 | Objections/Comments Received |
Apr 14, 2022 | Objections/Comments Received |
Apr 15, 2022 | Note to File |
Apr 19, 2022 | Correspondence Mailed/Faxed/E-mailed |
Apr 25, 2022 | Comments Received |
May 27, 2022 | Correspondence Received |
Aug 23, 2022 | Note to File |
Nov 29, 2022 | Additional Information Received |
Dec 16, 2022 | Correspondence Mailed/Faxed/E-mailed |
Jan 03, 2023 | Correspondence Mailed/Faxed/E-mailed |
Jan 03, 2023 | Correspondence Mailed/Faxed/E-mailed |
Jan 12, 2023 | Correspondence Mailed/Faxed/E-mailed |
Jan 13, 2023 | Objection withdrawal received |
Jan 13, 2023 | Correspondence Received |
Jan 20, 2023 | Correspondence Mailed/Faxed/E-mailed |
Jan 20, 2023 | Objection withdrawal received |
Jan 20, 2023 | Objection withdrawal received |
Jan 23, 2023 | Objection withdrawal received |
Jan 23, 2023 | Objection withdrawal received |
Feb 02, 2023 | Permit Approved |
Feb 02, 2023 | Biologist Report |
Oct 20, 2023 | Land Evidence Date |