Action Date | Action Description |
---|---|
May 18, 2022 | Assent Application Received |
May 18, 2022 | Administrative Review for Completeness |
May 31, 2022 | Additional Information Received |
Jun 01, 2022 | Application Accepted |
Jun 01, 2022 | Project Manager |
Jun 01, 2022 | Bio Team Review for Completeness |
Jun 29, 2022 | HPHC Review Pending |
Jun 29, 2022 | HPHC Historical Preservation No Effect |
Jul 05, 2022 | Biologist Report |
Jul 08, 2022 | Typist for Processing |
Jul 08, 2022 | Executive Sign Off |
Jul 08, 2022 | Sent to Photo Copy |
Jul 08, 2022 | Permit Approved |
Jul 08, 2022 | Permit Mailed |
Oct 18, 2023 | Duplicate Original Assent requested/mailed |
Nov 02, 2023 | Land Evidence Date |