Action Date | Action Description |
---|---|
Jun 21, 2022 | Assent Application Received |
Jun 24, 2022 | Administrative Review for Completeness |
Jun 28, 2022 | Bio Team Review for Completeness |
Jun 28, 2022 | Project Manager |
Jun 28, 2022 | Application Accepted |
Jul 22, 2022 | HPHC Review Pending |
Jul 22, 2022 | HPHC Historical Preservation No Effect |
Sep 14, 2022 | Additional Information Received |
Nov 29, 2022 | Engineering Report |
Nov 29, 2022 | Biologist Report |
Dec 05, 2022 | Typist for Processing |
Dec 05, 2022 | Executive Sign Off |
Dec 05, 2022 | Sent to Photo Copy |
Dec 05, 2022 | Permit Approved |
Dec 07, 2022 | Permit Mailed |
Dec 09, 2022 | Land Evidence Date |