Action Date | Action Description |
---|---|
Jun 30, 2022 | Freshwater Wetland - Preliminary Determination |
Jul 07, 2022 | Administrative Review for Completeness |
Jul 13, 2022 | Bio Team Review for Completeness |
Jul 13, 2022 | Application Accepted |
Jul 25, 2022 | Project Manager |
Aug 17, 2022 | HPHC Historical Preservation No Effect |
Sep 27, 2022 | Additional Information Requested from Applicant |
Feb 02, 2023 | Additional Information Received |
Feb 02, 2023 | Assent Application Received |
Mar 10, 2023 | HPHC Historical Preservation No Effect |
Apr 04, 2023 | Biologist Report |
Apr 18, 2023 | Typist for Processing |
Apr 18, 2023 | Executive Sign Off |
Apr 18, 2023 | Sent to Photo Copy |
Apr 18, 2023 | Permit Approved |
Apr 24, 2023 | Permit Mailed |
May 08, 2023 | Commencement of Work Notice received |
May 08, 2023 | Land Evidence Date |