Action Date | Action Description |
---|---|
Aug 25, 2022 | Preliminary Determination Request (Coastal) |
Sep 01, 2022 | Administrative Review for Completeness |
Sep 06, 2022 | Application Accepted |
Sep 07, 2022 | Bio Team Review for Completeness |
Sep 20, 2022 | Project Manager |
Sep 30, 2022 | Correspondence Mailed/Faxed/E-mailed |
Oct 04, 2022 | HPHC Historical Preservation No Effect |
Dec 16, 2022 | Additional Information Received |
Dec 16, 2022 | Assent Application Received |
Feb 06, 2023 | Biologist Report |
Feb 16, 2023 | Typist for Processing |
Feb 16, 2023 | Executive Sign Off |
Feb 16, 2023 | Sent to Photo Copy |
Feb 16, 2023 | Permit Approved |
Feb 17, 2023 | Permit Mailed |
Mar 13, 2023 | Land Evidence Date |