Action Date | Action Description |
---|---|
Oct 17, 2022 | Assent Application Received |
Oct 20, 2022 | Administrative Review for Completeness |
Nov 23, 2022 | Bio Team Review for Completeness |
Nov 23, 2022 | Deficient Application - Owner Notification Sent |
Jan 17, 2023 | Deficiency Response Received |
Feb 15, 2023 | Bio Team Review for Completeness |
Feb 15, 2023 | Additional Information Received |
Feb 15, 2023 | Application Accepted |
Feb 15, 2023 | Project Manager |
Mar 20, 2023 | HPHC Historical Preservation No Effect |
Jul 10, 2023 | Biologist Report |
Jul 11, 2023 | Typist for Processing |
Jul 11, 2023 | Executive Sign Off |
Jul 11, 2023 | Sent to Photo Copy |
Jul 11, 2023 | Permit Approved |
Jul 13, 2023 | Permit Mailed |
Oct 02, 2023 | Land Evidence Date |