Action Date | Action Description |
---|---|
Nov 16, 2022 | Assent Application Received |
Nov 21, 2022 | Administrative Review for Completeness |
Nov 21, 2022 | Bio Team Review for Completeness |
Dec 12, 2022 | Deficient Application - Owner Notification Sent |
Dec 12, 2022 | Eng Team Review for Completeness |
Feb 10, 2023 | Deficiency Response Received |
Feb 20, 2023 | Bio Team Review for Completeness |
Feb 23, 2023 | Eng Team Review for Completeness |
Feb 23, 2023 | Application Accepted |
Feb 23, 2023 | Project Manager |
Mar 09, 2023 | HPHC Historical Preservation No Effect |
Apr 12, 2023 | 30 day Public Notice Issued |
Apr 20, 2023 | 30 day Public Notice Issued |
May 12, 2023 | Public Notice End Date |
May 20, 2023 | Public Notice End Date |
Aug 01, 2023 | Dock/1.1.6 Review approval |
Aug 08, 2023 | Biologist Report |
Aug 30, 2023 | Engineering Report |
Aug 31, 2023 | Typist for Processing |
Aug 31, 2023 | Executive Sign Off |
Aug 31, 2023 | Sent to Photo Copy |
Aug 31, 2023 | Permit Approved |
Sep 06, 2023 | Permit Mailed |
Sep 12, 2023 | Commencement of Work Notice received |
Sep 29, 2023 | Land Evidence Date |