Action Date | Action Description |
---|---|
May 11, 2023 | Assent Application Received |
May 17, 2023 | Administrative Review for Completeness |
May 17, 2023 | Bio Team Review for Completeness |
May 17, 2023 | Project Manager |
May 17, 2023 | Application Accepted |
Jun 13, 2023 | HPHC Historical Preservation No Effect |
Jun 26, 2023 | Biologist Report |
Jun 29, 2023 | Typist for Processing |
Jun 29, 2023 | Executive Sign Off |
Jun 29, 2023 | Sent to Photo Copy |
Jun 29, 2023 | Permit Approved |
Jul 07, 2023 | Permit Mailed |
Jul 18, 2023 | Assent Correction Request Received |
Jul 27, 2023 | Commencement of Work Notice received |
Jul 27, 2023 | Land Evidence Date |