Action Date | Action Description |
---|---|
Jun 29, 2023 | Assent Application Received |
Jul 06, 2023 | Administrative Review for Completeness |
Jul 10, 2023 | Bio Team Review for Completeness |
Jul 12, 2023 | Deficient Application - Owner Notification Sent |
Jul 18, 2023 | Deficient Application Picked Up |
Jul 31, 2023 | Deficiency Response Received |
Jul 31, 2023 | Bio Team Review for Completeness |
Jul 31, 2023 | Application Accepted |
Jul 31, 2023 | Project Manager |
Aug 04, 2023 | HPHC Historical Preservation No Effect |
Aug 15, 2023 | Biologist Report |
Aug 17, 2023 | Typist for Processing |
Aug 17, 2023 | Executive Sign Off |
Aug 17, 2023 | Sent to Photo Copy |
Aug 17, 2023 | Permit Approved |
Aug 25, 2023 | Permit Mailed |
Sep 11, 2023 | Additional Information Received |
Sep 25, 2023 | Duplicate Original Assent requested/mailed |
Oct 11, 2023 | Land Evidence Date |