Action Date | Action Description |
---|---|
Aug 11, 2023 | Assent Application Received |
Aug 16, 2023 | Administrative Review for Completeness |
Aug 30, 2023 | Note to File |
Aug 30, 2023 | Additional Information Requested from Applicant |
Sep 05, 2023 | Certified Receipt Received |
Sep 06, 2023 | Correspondence Mailed/Faxed/E-mailed |
Sep 07, 2023 | Correspondence Mailed/Faxed/E-mailed |
Sep 07, 2023 | Correspondence Received |
Sep 22, 2023 | Correspondence Mailed/Faxed/E-mailed |
Sep 22, 2023 | Correspondence Received |
Sep 25, 2023 | Correspondence Received |
Oct 19, 2023 | Correspondence Mailed/Faxed/E-mailed |
Oct 19, 2023 | Correspondence Received |
Oct 24, 2023 | Correspondence Mailed/Faxed/E-mailed |
Oct 25, 2023 | Correspondence Mailed/Faxed/E-mailed |
Oct 25, 2023 | Correspondence Received |
Oct 25, 2023 | Application Accepted |
Oct 25, 2023 | Project Manager |
Oct 25, 2023 | Bio Team Review for Completeness |
Dec 06, 2023 | HPHC Historical Preservation Comments/Concerns |
Dec 13, 2023 | Biologist Report |
Dec 15, 2023 | Typist for Processing |
Dec 15, 2023 | Executive Sign Off |
Dec 15, 2023 | Sent to Photo Copy |
Dec 15, 2023 | Permit Approved |
Dec 18, 2023 | Permit Mailed |
Dec 28, 2023 | Land Evidence Date |