Action Date | Action Description |
---|---|
Aug 11, 2023 | Freshwater Wetlands Application - New - received |
Aug 16, 2023 | Administrative Review for Completeness |
Aug 29, 2023 | Bio Team Review for Completeness |
Aug 29, 2023 | Application Accepted |
Aug 29, 2023 | Project Manager |
Sep 25, 2023 | HPHC Historical Preservation No Effect |
Oct 03, 2023 | Biologist Report |
Oct 05, 2023 | Typist for Processing |
Oct 05, 2023 | Executive Sign Off |
Oct 05, 2023 | Sent to Photo Copy |
Oct 05, 2023 | Permit Approved |
Oct 06, 2023 | Permit Mailed |
Oct 25, 2023 | Land Evidence Date |
Nov 22, 2023 | Commencement of Work Notice received |