Action Date | Action Description |
---|---|
Oct 06, 2023 | Maintenance Certification Request |
Oct 12, 2023 | Administrative Review for Completeness |
Jan 16, 2024 | Eng Team Review for Completeness |
Jan 16, 2024 | Application Accepted |
Jan 16, 2024 | Project Manager |
Jan 30, 2024 | HPHC Historical Preservation No Effect |
Mar 07, 2024 | Plans Received |
Mar 26, 2024 | Typist for Processing |
Mar 26, 2024 | Executive Sign Off |
Mar 26, 2024 | Sent to Photo Copy |
Mar 26, 2024 | Permit Approved |
Mar 26, 2024 | Engineering Report |
Apr 02, 2024 | Permit Mailed |
Oct 18, 2024 | Land Evidence Date |