Action Date | Action Description |
---|---|
Land Evidence Date | |
Oct 19, 2023 | Assent Application Received |
Oct 19, 2023 | CHA Worksheet received |
Oct 24, 2023 | Administrative Review for Completeness |
Oct 30, 2023 | Bio Team Review for Completeness |
Oct 30, 2023 | Application Accepted |
Oct 30, 2023 | Project Manager |
Nov 24, 2023 | HPHC Historical Preservation No Effect |
Dec 19, 2023 | 30 day Public Notice Issued |
Jan 19, 2024 | Public Notice End Date |
Feb 14, 2024 | Comments Received |
Feb 28, 2024 | Mail Agenda Notice |
Mar 12, 2024 | Semi-Monthly Meeting Date Scheduled |
Jun 18, 2024 | Additional Information Received |
Aug 01, 2024 | Biologist Report |
Aug 01, 2024 | Engineering Report |
Aug 05, 2024 | Typist for Processing |
Aug 05, 2024 | Executive Sign Off |
Aug 05, 2024 | Sent to Photo Copy |
Aug 05, 2024 | Permit Approved |
Aug 07, 2024 | Permit Mailed |