Action Date | Action Description |
---|---|
Land Evidence Date | |
Nov 14, 2023 | Freshwater Wetlands Application - New - received |
Nov 16, 2023 | Administrative Review for Completeness |
Nov 20, 2023 | Bio Team Review for Completeness |
Nov 20, 2023 | Project Manager |
Nov 20, 2023 | Application Accepted |
Jan 05, 2024 | HPHC Historical Preservation Comments/Concerns |
Jan 24, 2024 | HPHC Historical Preservation No Effect |
Jan 29, 2024 | Biologist Report |
Jan 30, 2024 | Typist for Processing |
Jan 30, 2024 | Executive Sign Off |
Jan 30, 2024 | Sent to Photo Copy |
Jan 30, 2024 | Permit Approved |
Feb 01, 2024 | Permit Mailed |