Action Date | Action Description |
---|---|
Nov 24, 2023 | Assent Application Received |
Nov 28, 2023 | Administrative Review for Completeness |
Nov 29, 2023 | Eng Team Review for Completeness |
Nov 29, 2023 | Application Accepted |
Nov 29, 2023 | Project Manager |
Nov 29, 2023 | Category A* (Docks) |
Dec 05, 2023 | HPHC Historical Preservation No Effect |
Jan 02, 2024 | Plans Received |
Jan 10, 2024 | 30 day Public Notice Issued |
Feb 10, 2024 | Public Notice End Date |
Mar 14, 2024 | Engineering Report |
Mar 19, 2024 | Typist for Processing |
Mar 19, 2024 | Executive Sign Off |
Mar 19, 2024 | Sent to Photo Copy |
Mar 19, 2024 | Permit Approved |
Mar 21, 2024 | Permit Mailed |
Apr 09, 2024 | Commencement of Work Notice received |
Apr 12, 2024 | Land Evidence Date |
Jun 03, 2024 | Dock Post-Construction Certification by Engineer received. |