Action Date | Action Description |
---|---|
Monitoring Report | |
Dec 20, 2023 | Buffer Zone Management Application Received |
Dec 27, 2023 | Administrative Review for Completeness |
Jan 19, 2024 | Bio Team Review for Completeness |
Jan 22, 2024 | Deficient Application - Owner Notification Sent |
Feb 16, 2024 | Deficiency Response Received |
Feb 22, 2024 | Additional Information Received |
Mar 13, 2024 | Application Accepted |
Mar 13, 2024 | Project Manager |
Mar 13, 2024 | Bio Team Review for Completeness |
Apr 09, 2024 | HPHC Historical Preservation No Effect |
Apr 26, 2024 | Additional Information Requested from Applicant |
May 30, 2024 | Additional Information Received |
Jul 16, 2024 | Correspondence Mailed/Faxed/E-mailed |
Jul 26, 2024 | Plans Received |
Aug 14, 2024 | Biologist Report |
Aug 19, 2024 | Typist for Processing |
Aug 19, 2024 | Executive Sign Off |
Aug 19, 2024 | Sent to Photo Copy |
Aug 19, 2024 | Permit Approved |
Aug 20, 2024 | Permit Mailed |
Sep 04, 2024 | Land Evidence Date |
Oct 01, 2024 | Commencement of Work Notice received |