Action Date | Action Description |
---|---|
Jan 22, 2024 | Buffer Zone Management Application Received |
Jan 26, 2024 | Administrative Review for Completeness |
Feb 06, 2024 | Bio Team Review for Completeness |
Feb 06, 2024 | Deficient Application - Owner Notification Sent |
Mar 22, 2024 | Deficiency Response Received |
Apr 18, 2024 | Bio Team Review for Completeness |
Apr 18, 2024 | Application Accepted |
Apr 18, 2024 | Project Manager |
May 06, 2024 | Additional Information Requested from Applicant |
May 07, 2024 | HPHC Historical Preservation No Effect |
May 16, 2024 | Additional Information Received |
Jun 11, 2024 | Additional Information Requested from Applicant |
Jun 12, 2024 | Correspondence Received |
Jun 12, 2024 | Correspondence Mailed/Faxed/E-mailed |
Aug 13, 2024 | Plans Received |
Aug 13, 2024 | Correspondence Mailed/Faxed/E-mailed |
Aug 21, 2024 | Biologist Report |
Aug 22, 2024 | Typist for Processing |
Aug 22, 2024 | Executive Sign Off |
Aug 22, 2024 | Sent to Photo Copy |
Aug 22, 2024 | Permit Approved |
Aug 23, 2024 | Permit Mailed |
Aug 27, 2024 | Commencement of Work Notice received |
Oct 11, 2024 | Land Evidence Date |