Action Date | Action Description |
---|---|
Jan 31, 2024 | Freshwater Wetlands Application - New - received |
Feb 06, 2024 | Administrative Review for Completeness |
Feb 23, 2024 | Eng Team Review for Completeness |
Feb 23, 2024 | Bio Team Review for Completeness |
Feb 23, 2024 | Application Accepted |
Feb 23, 2024 | Project Manager |
Mar 22, 2024 | HPHC Historical Preservation No Effect |
Apr 22, 2024 | Biologist Report |
Apr 24, 2024 | Engineering Report |
Apr 26, 2024 | Typist for Processing |
Apr 26, 2024 | Executive Sign Off |
Apr 26, 2024 | Sent to Photo Copy |
Apr 26, 2024 | Permit Approved |
Apr 30, 2024 | Permit Mailed |
May 31, 2024 | Land Evidence Date |
Oct 17, 2024 | Commencement of Work Notice received |