Action Date | Action Description |
---|---|
Assent Requirement | |
Jan 31, 2024 | CHA Worksheet received |
Jan 31, 2024 | Assent Application Received |
Feb 07, 2024 | Administrative Review for Completeness |
Feb 09, 2024 | Bio Team Review for Completeness |
Feb 09, 2024 | Application Accepted |
Feb 09, 2024 | Project Manager |
Mar 15, 2024 | HPHC Historical Preservation No Effect |
May 02, 2024 | Additional Information Received |
May 14, 2024 | Biologist Report |
May 28, 2024 | Typist for Processing |
May 28, 2024 | Executive Sign Off |
May 28, 2024 | Sent to Photo Copy |
May 28, 2024 | Permit Approved |
May 30, 2024 | Permit Mailed |
May 31, 2024 | Land Evidence Date |
Jun 14, 2024 | Note to File |