Action Date | Action Description |
---|---|
Biologist Report | |
US Army Corps of Engineers Approval Required | |
Feb 29, 2024 | Assent Application Received |
Mar 06, 2024 | Administrative Review for Completeness |
Mar 12, 2024 | Bio Team Review for Completeness |
Mar 12, 2024 | Project Manager |
Mar 12, 2024 | Application Accepted |
Mar 12, 2024 | Category A* (Docks) |
Apr 23, 2024 | HPHC Historical Preservation No Effect |
Jul 17, 2024 | 30 day Public Notice Issued |
Aug 13, 2024 | Comments Received |
Aug 17, 2024 | Public Notice End Date |
Aug 22, 2024 | Objections/Comments Received |
Aug 22, 2024 | Correspondence Received |
Aug 24, 2024 | Public Notice End Date Extension Granted |
Oct 28, 2024 | Correspondence Received |