Action Date | Action Description |
---|---|
Mar 01, 2024 | CHA Worksheet received |
Mar 01, 2024 | Assent Application Received |
Mar 07, 2024 | Administrative Review for Completeness |
Mar 13, 2024 | Bio Team Review for Completeness |
Mar 13, 2024 | Project Manager |
Mar 13, 2024 | Additional Information Requested from Applicant |
Mar 13, 2024 | Application Accepted |
Apr 03, 2024 | Plans Received |
Apr 16, 2024 | HPHC Historical Preservation No Effect |
Aug 02, 2024 | Additional Information Received |
Aug 28, 2024 | Biologist Report |
Aug 29, 2024 | Typist for Processing |
Aug 29, 2024 | Executive Sign Off |
Aug 29, 2024 | Sent to Photo Copy |
Aug 29, 2024 | Permit Approved |
Sep 03, 2024 | Permit Mailed |
Sep 10, 2024 | Land Evidence Date |
Oct 24, 2024 | Commencement of Work Notice received |