Action Date | Action Description |
---|---|
Land Evidence Date | |
Mar 08, 2024 | Freshwater Wetlands Application - New - received |
Mar 18, 2024 | Administrative Review for Completeness |
Mar 21, 2024 | Bio Team Review for Completeness |
Mar 21, 2024 | Project Manager |
Mar 21, 2024 | Application Accepted |
Apr 16, 2024 | HPHC Historical Preservation No Effect |
Jun 20, 2024 | Additional Information Requested from Applicant |
Jul 08, 2024 | Correspondence Received |
Jul 08, 2024 | Correspondence Mailed/Faxed/E-mailed |
Aug 13, 2024 | Additional Information Received |
Aug 21, 2024 | Biologist Report |
Aug 22, 2024 | Typist for Processing |
Aug 22, 2024 | Executive Sign Off |
Aug 22, 2024 | Sent to Photo Copy |
Aug 22, 2024 | Permit Approved |
Aug 23, 2024 | Permit Mailed |