Action Date | Action Description |
---|---|
Apr 01, 2024 | Maintenance Certification Request |
Apr 05, 2024 | Administrative Review for Completeness |
Jun 06, 2024 | Eng Team Review for Completeness |
Jun 06, 2024 | Bio Team Review for Completeness |
Jun 06, 2024 | Application Accepted |
Jun 06, 2024 | Project Manager |
Jun 12, 2024 | Fee Waiver Granted |
Jun 14, 2024 | Plans Received |
Jul 01, 2024 | HPHC Historical Preservation No Effect |
Jul 11, 2024 | Biologist Report |
Jul 19, 2024 | Typist for Processing |
Jul 19, 2024 | Executive Sign Off |
Jul 19, 2024 | Sent to Photo Copy |
Jul 19, 2024 | Permit Approved |
Jul 23, 2024 | Permit Mailed |
Oct 18, 2024 | Land Evidence Date |