Action Date | Action Description |
---|---|
Apr 10, 2024 | Assent Application Received |
Apr 16, 2024 | Administrative Review for Completeness |
Apr 25, 2024 | Bio Team Review for Completeness |
Apr 25, 2024 | Eng Team Review for Completeness |
Apr 25, 2024 | Deficient Application - Owner Notification Sent |
May 01, 2024 | Deficiency Response Received |
May 06, 2024 | Eng Team Review for Completeness |
May 06, 2024 | Application Accepted |
May 10, 2024 | Project Manager |
May 13, 2024 | Engineering Report |
May 13, 2024 | Finding Of No Significant Impact (FONSI) |
May 13, 2024 | Permit Mailed |
May 14, 2024 | HPHC Historical Preservation No Effect |