Action Date | Action Description |
---|---|
May 07, 2024 | Assent Application Received |
May 14, 2024 | Administrative Review for Completeness |
May 15, 2024 | Eng Team Review for Completeness |
May 15, 2024 | Project Manager |
May 15, 2024 | Application Accepted |
Jun 17, 2024 | HPHC Historical Preservation No Effect |
Jul 02, 2024 | 30 day Public Notice Issued |
Aug 02, 2024 | Public Notice End Date |
Aug 02, 2024 | Additional Information Received |
Oct 17, 2024 | Engineering Report |
Oct 18, 2024 | Typist for Processing |
Oct 18, 2024 | Executive Sign Off |
Oct 18, 2024 | Sent to Photo Copy |
Oct 18, 2024 | Permit Approved |
Oct 21, 2024 | Permit Mailed |
Nov 04, 2024 | Land Evidence Date |