Action Date | Action Description |
---|---|
Assent Requirement | |
May 13, 2024 | Assent Application Received |
May 13, 2024 | CHA Worksheet received |
May 15, 2024 | Administrative Review for Completeness |
Jun 03, 2024 | Bio Team Review for Completeness |
Jun 06, 2024 | Deficient Application - Owner Notification Sent |
Jun 12, 2024 | Correspondence Received |
Jun 13, 2024 | Correspondence Mailed/Faxed/E-mailed |
Jul 05, 2024 | Deficiency Response Received |
Jul 15, 2024 | Bio Team Review for Completeness |
Jul 15, 2024 | Application Accepted |
Jul 15, 2024 | Project Manager |
Aug 07, 2024 | HPHC Historical Preservation No Effect |
Aug 21, 2024 | Biologist Report |
Aug 22, 2024 | Typist for Processing |
Aug 22, 2024 | Executive Sign Off |
Aug 22, 2024 | Sent to Photo Copy |
Aug 22, 2024 | Permit Approved |
Aug 26, 2024 | Permit Mailed |
Sep 11, 2024 | Land Evidence Date |