Action Date | Action Description |
---|---|
Jan 14, 1999 | Application Accepted |
Jan 26, 1999 | Historical Preservation Approval Granted |
Feb 26, 1999 | 30 day Public Notice Issued |
May 12, 1999 | Biologist Report |
May 12, 1999 | Engineering Report |
May 25, 1999 | Meeting Held |
Jun 08, 1999 | Meeting Held |
Jun 29, 1999 | Meeting Held |
Aug 10, 1999 | Meeting Held |
Nov 23, 1999 | Council Decision Made |
Jan 24, 2000 | 30 Day Appeal Notification to Owner |
Dec 23, 2005 | Correspondence Mailed/Faxed/E-mailed |
Nov 22, 2006 | 30-Day Notification of Cancellation letter |
Nov 28, 2006 | Certified Receipt Received |
Dec 22, 2006 | Correspondence Received |
Jan 31, 2007 | Correspondence Mailed/Faxed/E-mailed |
Mar 29, 2007 | Correspondence Received |
Aug 20, 2007 | Correspondence Received |
Sep 04, 2007 | Correspondence Received |
Jan 25, 2008 | Correspondence Mailed/Faxed/E-mailed |
Feb 13, 2008 | Additional Information Received |
Feb 18, 2008 | Conservation Easement Mailed. |
Mar 20, 2008 | Conservation Easement Recording received |
Sep 09, 2008 | Additional Information Received |
Oct 27, 2008 | Plans Received |
Oct 28, 2008 | Typist for Processing |
Oct 28, 2008 | Executive Sign Off |
Oct 28, 2008 | Sent to Photo Copy |
Oct 28, 2008 | Permit Approved |
Oct 28, 2008 | Stipulation Package from Biologist |
Oct 28, 2008 | Stipulation Package by Engineer |
Dec 03, 2008 | Land Evidence Date |
Oct 04, 2017 | Commencement of Work Notice received |