Action Date | Action Description |
---|---|
Jul 13, 2001 | Application Accepted |
Jul 19, 2001 | Historical Preservation Approval Granted |
Aug 01, 2001 | 30 day Public Notice Issued |
Sep 12, 2001 | Engineering Report |
Sep 13, 2001 | Biologist Report |
Sep 28, 2001 | Dock sub-committee Approved |
Oct 01, 2001 | Permit Approved |
Sep 10, 2015 | Modification Request |
Sep 11, 2015 | Administrative Review for Completeness |
Sep 14, 2015 | Team Review for Completeness |
Sep 16, 2015 | Biologist Report |
Oct 06, 2015 | 30 day Public Notice Issued |
Oct 29, 2015 | Objections/Comments Received |
Oct 29, 2015 | Plans Received |
Nov 06, 2015 | Public Notice End Date |
Nov 17, 2015 | Typist for Processing |
Nov 17, 2015 | Executive Sign Off |
Nov 17, 2015 | Sent to Photo Copy |
Nov 17, 2015 | Permit Approved |
Dec 03, 2015 | US Army Corps of Engineers Approval Received |
Dec 18, 2015 | Land Evidence Date |