Action Date | Action Description |
---|---|
May 23, 2002 | Application Accepted |
Jun 01, 2002 | 30 day Public Notice Issued |
Oct 15, 2003 | Additional Information Requested from Applicant |
Oct 29, 2003 | Correspondence Received |
Aug 01, 2005 | Executive Sign Off |
Aug 18, 2005 | Ready to Schedule Semi-Monthly Meeting |
Aug 18, 2005 | Mail Agenda Notice |
Aug 23, 2005 | Semi-Monthly Meeting Held |
Aug 23, 2005 | Council Approval Granted |
Aug 23, 2005 | Semi-Monthly Meeting Date Scheduled |
Sep 15, 2005 | Stipulation Package by Engineer |
Sep 16, 2005 | Modification Approved |
Sep 16, 2005 | Typist for Processing |
Sep 16, 2005 | Executive Sign Off |
Sep 16, 2005 | Sent to Photo Copy |
Sep 19, 2005 | Engineering Report |
Sep 19, 2005 | Legal Response/Decision |
Sep 29, 2005 | Land Evidence Date |
Jun 08, 2006 | Commencement of Work Notice received |